This project supports Valley Water’s ongoing vegetation control and sediment removal activities that reduce flood risk by maintaining the design conveyance capacity of flood protection projects. The project includes controlling in-stream vegetation and tree growth and removing sediment at appropriate intervals. Before carrying out in-stream maintenance, Valley Water’s personnel perform biological pre-construction surveys to minimize environmental impacts. This project also helps fund future maintenance of flood protection projects completed under the Safe, Clean Water Program.
This project comprises two (2) sub-projects that support Valley Water’s ongoing vegetation control and sediment removal activities. These sub-projects are:
-
F1.1 Vegetation Control for Capacity
-
F1.2 Sediment Removal for Capacity
KPI #1: Maintain completed flood protection projects for flow conveyance.
F1.1: Vegetation Control for Capacity
In FY24, Valley Water completed 2,126 acres of in-stream vegetation management to reduce flood risk along 173 miles of streams throughout the county using an integrated combination of mechanical, hand labor, and herbicide methods.
F1.2: Sediment Removal for Capacity
In FY24, Valley Water removed approximately 54,452 cubic yards of sediment on 22 projects from various creeks throughout the county to maintain design capacity.
**In addition, Valley Water also removed 1,260 cubic yards of sediment from Berryessa Creek to maintain design capacity in FY24 Q1. However, this work was charged to a FEMA cost recovery project (EOC-Storm 22-12-30) and is not represented in the Project F1 sediment totals.
August 2024
Example Vegetation Removal
Key Performance Indicator (FY22-36)
-
Maintain completed flood protection projects for flow conveyance.
Benefits
-
Ensures that existing flood protection projects continue to provide flood protection
-
Improves water quality
Geographic Area of Benefit
Countywide
About the Safe, Clean Water and Natural Flood Protection Program
In November 2020, voters in Santa Clara County overwhelmingly approved Measure S, a renewal of Valley Water’s Safe, Clean Water and Natural Flood Protection Program.
The program was first passed by voters in 2000 as the Clean, Safe Creeks and Natural Flood Protection Plan, then again in 2012 as the Safe, Clean Water and Natural Flood Protection Program. The renewal of the Safe, Clean Water Program will continue to provide approximately $47 million annually for local projects that deliver safe, clean water, natural flood protection, and environmental stewardship to all the communities we serve in Santa Clara County.
While evaluating ways to improve the 2012 program, Valley Water gathered feedback from more than 21,000 community members. That helped Valley Water create the six priorities for the renewed Safe, Clean Water Program, which are:
Priority A: Ensure a Safe, Reliable Water Supply
Priority B: Reduce Toxins, Hazards and Contaminants in our Waterways
Priority C: Protect our Water Supply and Dams from Earthquakes and Other Natural Disasters
Priority D: Restore Wildlife Habitat and Provide Open Space
Priority E: Provide Flood Protection to Homes, Businesses, Schools, Streets and Highways
Priority F: Support Public Health and Public Safety for Our Community
Each year, Valley Water prepares a report providing a progress update for each of these program priorities, along with fiscal year accomplishments.
To ensure transparency and accountability to the voters, the ballot measure also created an Independent Monitoring Committee, appointed by the Santa Clara Valley Water District Board of Directors. The Independent Monitoring Committee annually reviews the program’s progress to ensure the outcomes are achieved in a cost-efficient manner and reports its findings to the Board. Additionally, the IMC also reviews each proposed 5-year implementation plan prior to its submittal for Board approval.
In addition, the program requires three independent audits.