Design-Build and P3

October 2016 Update: Design Build/P3 Dual Track Procurement Process for Expedited Purified Water Program (Program)

Santa Clara Valley Water District - Expedited Purified Water Program
The Expedited Purified Water Program (Program) is part of the District’s strategy to respond to the current drought and is consistent with Board direction to expand the County’s water supply. As currently conceived, the Program could provide up to 45,000 acre-feet per year (AFY) of purified water for indirect and/or direct potable reuse to supplement groundwater recharge from other existing sources, such as imported and locally-stored water supply.

The Program consists of several key components:

    1.  Silicon Valley Advanced Water Purification Center (SVAWPC) Expansion; 
    2.  Ford Recharge Ponds Indirect Potable Reuse Facility; 
    3.  Mid-Basin Injection Wells; 
    4.  Los Gatos Recharge Ponds; 
    5.  Westside Injection Wells (or central pipeline direct potable reuse as a future alternative); 
    6.  Sunnyvale Indirect Potable Reuse.

Design Build Location Map

Click on map to enlarge image

Estimated Capacities and Costs (2014 dollars)

Proposed Purified Water Program Components Description

Capacity (AFY)

Est. Capital Costs ($M)6

Est. Total O&M Costs ($M/year)

Ford Recharge Ponds IPR1

4,200

$70

$4.0

Mid-Basin Injection Wells IPR2

5,600

$140

$3.5

Los Gatos Recharge Ponds IPR3

20,200

$260

$10.0

Westside Injection Wells IPR4
(or Central Pipeline DPR)

5,000
(5,000)

$120
($65)

$4.0
($4.5)

Sunnyvale IPR 5

10,000

$210

$2.0

Total

45,000

$800

$23.5


October 2016 Update: Design Build/P3 Dual Track Procurement Process for Expedited Purified Water Program (Program) 

As reflected in the individual sections below, a Request for Qualifications (RFQ) process was undertaken between January and June 2016. The list of respondents and final shortlists for two design-build RFQs and one P3 RFQ were posted in April and June, 2016, respectively.

The Board’s Recycled Water Committee (RW Committee), comprised of 3 of the 7 Board members, held meetings on the following dates in 2016:

1. March 1
2. May 12
3. July 9
4. July 19
5. September 7

Staff has provided Program development updates to the RW Committee at most of these meetings (click on dates above for Meeting Agendas and Minutes). At the May 12, 2016 RW Committee Meeting, staff recommended, and Committee members agreed, that one procurement track should be selected by the full Board before Requests for Proposals (RFPs) are published to the shortlisted entities.

At the September 7, 2016 RW Committee Meeting, staff presented both qualitative and quantitative evaluation and analyses of the Design Build and P3 delivery methods, and made a staff recommendation to choose the Progressive Design Build method. The Committee considered staff’s evaluation and recommendation, and directed staff to make the presentation to the full Board on September 20, 2016.

The full Board received staff’s presentation and heard from representatives of the two shortlisted P3 entities. The Board made no decision, but directed staff to return at a later date and to arrange for representatives of other water agencies who have used either a DB or P3 delivery method on one or more of their capital projects to attend this next Board meeting. The Board desires to hear directly from these agencies as to the motivators/circumstances/reasons for the choice(s) of delivery method they made and their experience with the project’s process and outcome.

Staff is in the process of arranging another special Board meeting, which will likely be held in early 2017. If the Board chooses a project delivery method in early 2017, release of the RFPs to the appropriate shortlist(s) will follow in 2 to 4 months.


Design Build and P3 Dual-Track Procurement Process


The District plans to solicit Statements of Qualification in parallel for both the progressive design-build (PDB) project delivery approach and for the public-private-partnership (P3) project delivery method.

To be placed on the Outreach List please fill out the form in the link below. To view the most up-to-date Outreach List please see the link below.

PDB Silicon Valley Advanced Water Purification Center (SVAWPC) Expansion
    
Request for Qualifications (1-15-16)
    Preproposal Meeting (2-11-16)
    Attachment A - Project Background Documents
            1.) SBWR Strategic and Master Planning Volume 1 Report
            2.) SBWR Strategic and Master Planning Volume 2 Appendices
            3.) South Bay Advanced Recycled Water Treatment Facility (or AWT) Engineer's Report
            4.) South Bay Advanced Recycled Water Treatment Facility Engineer's Report - Appendices
    Attachment E - SOQ Forms (Ver.A dated 3/9/16)
    Attachment E - Part VII Financial Capability Evaluation Template (Ver.A dated 3/15/16)
    Addendum #1 (Issued 01-28-16)
    Addendum #2 (Issued 02-10-16)
    Addendum #3 (Issued 02-23-16)
    Addendum #4 (Issued 03-10-16)
    Addendum #5 (Issued 03-17-16)
    Addendum #6 (Issued 03-24-16)
    Addendum #7 (Issued 05-19-16)
    SVAWPC Respondent Information (4-16-16)
    Proposed Shortlist (5-31-16)
    Final Shortlist (6-21-16)


PDB Purified Water Pipeline (SVAWPC to Los Gatos Recharge Ponds)
    Request for Qualifications (1-15-16)
    Preproposal Meeting (2-11-16)
    Attachment A - Project Background Documents
    1.) Draft Technical Memorandum on Conveyance Pipeline Facilities – Preliminary Assessment Methodology (Part 1 of 3)
    2.) Draft Technical Memorandum on Conveyance Pipeline Facilities – Attachments A,B,C,E,F (Part 2 of 3)
    3.) Draft Technical Memorandum on Conveyance Pipeline Facilities – Attachment D Preliminary Geotechnical 
         Review (Part 3 of 3)

    Attachment E - SOQ Forms (Ver. B dated 3/17/16)
    Attachment E - Part VII Financial Capability Evaluation Template (Ver.A dated 3/15/16)
    Addendum #1 (Issued 01-28-16) 
    Addendum #2 (Issued 02-10-16)
    Addendum #3 (Issued 02-23-16)
    Addendum #4 (Issued 03-10-16)
    Addendum #5 (Issued 03-17-16)
    Addendum #6 (Issued 03-24-16)
    Addendum #7 (Issued 05-19-16)
    PWPL Respondent Information (4-16-16)
    Proposed Shortlist (5-31-16)
    Final Shortlist (6-21-16)

P3 Expedited Recycled and Purified Water Program

    Request for Qualifications (1-15-16)
    Attachment E - Part V: Financial Capability Evaluation Template (v.2)
    Preproposal Meeting (2-11-16)
    Addendum #1 (Issued 01-28-16)
    Addendum #2 (Issued 02-10-16)
    Addendum #3 (Issued 02-23-16)
    Addendum #4 (Issued 03-17-16)
    Addendum #5 (Issued 05-19-16)
    P3 Respondent Information (4-16-16)
    Proposed Shortlist (5-31-16)
    Final Shortlist (6-21-16)

Progressive Design-Build (PDB) Procurement Process

The District plans to solicit two Statements of Qualification (SOQ) for the following Program components using progressive design-build (PDB) project delivery: 

    1.  91884009 – Silicon Valley Advanced Water Purification Center (SVAWPC) Expansion 
    2.  91384001 – Purified Water Pipeline – from SVAWPC to Los Gatos Recharge Ponds

Soliciting two separate SOQs will enable selection of the most qualified teams for each Program component and will spread the design and construction work among various interested firms. The following components have been completed for the procurement process: 

    1.  Solicitation for PDB SOQs for two Program components – January 2016 
    2.  SOQ evaluations and final shortlisting of up to three qualifying entities for each Program component – June 2016 
   
Public-Private Partnership (P3) Procurement Process

In parallel with the above-described PDB procurement process, the District plans to solicit Statements of Qualification (SOQ) for a public-private partnership (P3) project delivery approach for the Program.

The following components have been completed for the procurement process: 

    1.  Solicitation for P3 SOQs for the Program – January 2016 
    2.  SOQ evaluations and final shortlisting of up to three qualifying entities – June 2016 
  
Related Reports and Presentations

Related Board Agenda Memorandums